TCCH TCCH new building

67% Complete

Project Description

TCCH is relocating to a new building on court st in Pasco. Bellas has been tasked with design and furnishing of the private office spaces and cubicles.

Documents

Project Progress

67% Progress

100% Timing

Start Date

04/01/2017

End Date

04/30/2017

0/1

Approved Documents

2/3

Complete Milestones

2/3

Complete Phases

9/16

Complete Tasks

Milestones

2 / 3 Completed

67%

  • 20% All furniture Delivered04/10/2017 Bella Wood and cubicals are in their place ready to be built
  • 40% Cubicals built04/14/2017 Sections 1-5 cubicals built
  • 70% All furniture installed04/21/2017 Private offices and cubicals built and furnished

Phases

Expand Discussions | 2 / 3 Completed

Moving furniture into office spaces 0 Documents 4 / 4 Tasks 0 Responses

100%
Description

Shipment of all furniture from Bellas to their proper places for staging.

4 of 4 completedTasks

  • Receive shipment of Bella Wood furniture 04/03/2017
  • Pull and prep cubical panels 04/04/2017
  • Pull and prep cubical work surfaces 04/05/2017
  • Move cubical and office materials to TCCH 04/14/2017

of 0 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

Your email address will not be published. Required fields are marked *

Build cubicals 0 Documents 5 / 5 Tasks 0 Responses

100%
Description

Construction of all cubicals

5 of 5 completedTasks

  • Section 1 cubicals built 04/14/2017
  • Section 2 cubicals built 04/14/2017
  • Section 3 cubicals built 04/14/2017
  • Section 4 cubicals built 04/14/2017
  • Section 5 cubicals built 04/14/2017

of 0 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

Your email address will not be published. Required fields are marked *

Build Bella Wood in private offices 0 Documents 0 / 7 Tasks 0 Responses

0%
Description

Construction of all Bella Wood in private offices

0 of 7 completedTasks

  • CEO office 04/17/2017
  • COO office 04/17/2017
  • Executive assistant 04/17/2017
  • Director of quality 04/18/2017
  • Director of behavior health 04/18/2017
  • Director of operations 04/18/2017
  • HR director 04/18/2017

of 0 Approved No Documents Documents

No documents attached to this phase.

Discussion 0 Responses

Leave a Reply

Your email address will not be published. Required fields are marked *

Project Discussion 2 Responses to TCCH

  1. 04/12/2017 at 12:10 AM
    austin tiniud

    ok

  2. 04/12/2017 at 12:05 AM
    austin tiniud

    sure, i’ll do that shortly

Leave a Reply

Your email address will not be published. Required fields are marked *

Update Status

Document Status Updated

Notifications have been sent.